Section 1 Need for guidelines
Section 2 Definitions
Section 3 Action required by companies Section 4 Summary of DTI process
Appendix A Application Checklist
Appendix B Consent to deposit materials on the seabed (Depcon)
Appendix C Consent for the discharge of the contents of a pipeline into the sea
Appendix D Useful addresses
Since the Guidance Notes for Petroleum and Submarine Pipelines were published in 1992 there have been some legislative changes. The Pipeline Safety Regulations 1996 were introduced by the Health and Safety Executive; as part of a consolidation exercise, the Petroleum Act 1998 repealed and replaced the Petroleum and Submarine Pipelines Act 1975 and the Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations came into effect in 1999. All have had an impact in the process of making an application for an offshore Pipeline Works Authorisation (PWA).
Please note that a Pipeline Works Authorisation should have been issued before construction of a pipeline or pipeline system begins. It is recommended that, before submitting an application, the prospective owner should informally consult both Pipelines Administration in DTI and the Health and Safety Executive at the earliest possible opportunity, to discuss the proposed scheme and the regulatory requirements involved. (For addresses and telephone numbers please see Appendix D).
Where there are no objections it takes approximately four months from receipt of the application to issuing the authorisation. In the case of pipelines in respect of which an environmental statement is required under the Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999, the procedure may take longer in order for all the environmental issues to be properly considered. Further guidance on the effect of the 1999 Regulations can be found in the Environment section of this web site. Operators are therefore urged to submit their applications in good time to meet their deadlines.
Offshore Pipeline
Under the Petroleum Act 1998 an authorisation is required for the construction and/or use of a "pipeline" in controlled waters.
A pipeline is defined as a pipe or system of pipes "for the conveyance of any thing, together with any apparatus and works associated with such a pipe or system". This includes pipelines used for the conveyance of hydrocarbons, water and chemicals. However, although other consents may be required for their construction/use, electric cables, drains and sewers are not pipelines under the 1998 Act, nor are hydraulic control lines or umbilicals of hydraulic controls.
Controlled waters means the UK territorial sea and any part of the sea on the UK continental shelf.
Holder of the PWA
The holder is the person to whom the authorisation is issued. An authorisation may not be issued to a person other than a body corporate.
The Users of a Pipeline
The users are the persons authorised by the PWA to use the pipeline for the purpose of conveying any fluid so authorised.
The Operator of a Pipeline
The operator is the person designated by the holder to be responsible for organising or supervising the construction or operation of the authorised pipeline in a manner which complies with the authorisation and, inter alia, with any relevant legislation existing at the material time. The works authorisation may name the operator as the holder.
Owner of the Pipeline
DTI requests details of the owner(s) in the application and in future these will be listed in the PWA. The Petroleum Act 1998 allows the Secretary of State to make an order, designating a person as the "owner" of a pipeline, after giving the person concerned an opportunity of being heard on the subject.
Pipeline Works Authorisation (PWA)
Under the Petroleum Act 1998 a "works authorisation" means an authorisation:
a. for the works for the construction of a pipeline;
b. for such works and for the use of the pipeline.
Deposit of Materials on the Seabed Consent (DEPCON)
Required before any materials e.g. rocks/ mattresses are placed on the seabed during construction of a pipeline or in order to maintain such a pipeline. (Full details Appendix B.)
Consent for Discharge of the contents of a Pipeline into the Sea (DISCON)
Required before a line is filled with chemicals or before any discharge (other than untreated seawater or sweet water) takes place. (Full details in Appendix C.)
Application Checklist
Cover (NO RING BINDERS PLEASE):
Administrative Detail
OR
AND
Technical Details
PLUS
18 copies of the above are required (19 if the project is within Territorial Waters). Three copies of the Navigational Charts must be in colour.
Consent to deposit materials on the seabed (Depcon)
The permanent placing or deposition of materials such as gravel, rock, mattresses or protective pipeline covers on the seabed during the construction of a pipeline is governed by the Pipeline Works Authorisation. Schedule 2 of the authorisation prohibits any further deposition except with the prior written consent of the Secretary of State.
For pipelines which do not have a PWA, for example, pipelines constructed prior to the coming into force of the Petroleum and Submarine Pipelines Act 1975, any deposition would require a licence under the Food and Environmental Protection Act 1985 (FEPA). (Part II of FEPA only exempts from its provisions anything done "for the purpose of constructing or maintaining a pipeline as respects any part of which an authorisation is in force".)
FEPA is administered by the Ministry of Agriculture, Fisheries and Food (MAFF) as regards England and Wales, by the Scottish Executive Marine Laboratory on behalf of the DTI as regards Scotland and by the Department of Agriculture for Northern Ireland (DANI) as regards Northern Ireland. Applications for licences under FEPA should be made direct to the relevant Department.
Applications for consent to deposit materials under a PWA should be made to Offshore Pipelines
Administration at the DTI and copied to Health and Safety Executive on Form Depcon1. Where appropriate (simple) drawings showing where, for example, mattresses are to be placed, should accompany the form.
The information required by the form includes -
i. a description of the material to be deposited
ii. the quantity to be deposited
iii. in the case of rocks, the maximum size to be deposited
iv. the location of the proposed site.
In addition, the following further details are required -
When a consent for a deposition of materials is given, it usually contains terms reserving to the Secretary of State the right to require removal of any materials deposited should they become a potential or actual hazard or obstruction to other seabed users. Removal may also be required at the end of the useful life of the pipeline.
The pipeline owner should consult relevant fishing organisations and other seabed users before any operation to deposit materials is begun and keep appropriate Government Departments advised of agreements reached. (This is usually covered in discussion with the fishermen about the pipeline project as a whole).
Please note that if any preparatory work, for example pipeline crossings, are to be put in place prior to the construction of the pipeline, the PWA should be requested early enough to undertake this work, otherwise a FEPA licence may be required. As stated above, it is only activities "for the purpose of constructing or maintaining a pipeline as respects any part of which an authorisation is in force" which are exempt from the provisions of FEPA.
Sample Depcon 1
[PIPELINE(S) / PROJECT NAME]
Details for Deposit Consent: Form DepCon 1
| Col 1 | Col 2 | Col 3 | Col 4 | Col 5 | Col 6 | Col 7 |
| Pipeline Number | Proposed Date (month and year) |
Type & Size of Materials | Quantity | Location of Deposit | Drawing Number (if applicable) |
|
| From: | To: | |||||
Consent for the discharge of the contents of a pipeline into the sea.
The discharge from a pipeline of substances, excluding untreated sea water or sweet water (but including untreated sea water or sweet water which may contain unquantified amounts of mill -scale or rust), into any waters in or around the United Kingdom is prohibited without an appropriate consent or licence.
The specific consent requirements in respect of discharges from a pipeline into the sea depend upon whether the pipeline in question is the subject of a Pipeline Works Authorisation. The position is as follows:
a. for pipelines built prior to the coming into force of the Petroleum and Submarine Pipelines Act 1975
(i.e. where no authorisation exists) discharges are subject to the Food and Environment Protection Act 1985 (FEPA) and would require a licence under that Act. (FEPA is administered by MAFF for discharges in English and Welsh waters, by SERAD - Marine Laboratory on behalf of the DTI in Scottish waters and by DANI for discharges in Northern Ireland waters)b. pipelines which have a Pipeline Works Authorisation are exempt from the requirements of FEPA.
However, under the terms of the works authorisation, the prior written consent of the Secretary of State is necessary before a discharge can take place and an application for that consent should be made on Form DisCon1 to Pipelines Administration at the DTI.
In both cases, in determining whether to allow the operational discharge of pipeline substances into controlled waters regard would be given to the need:
i. to protect the marine environment, the living resources which it supports and human health;
and ii. to prevent interference with other legitimate users of the sea.
Notification of line fill and discharge
To hasten the process of issuing a discharge consent, prior notification of intended line fill should be given in all cases to Environmental Section at the DTI and the Health and Safety Executive, also to MAFF, SERAD, Marine Laboratory or DANI as appropriate.
[A minimum of three weeks notice should be given. It is advisable that notification takes place as early as possible, as recommendations may include advice on the use of alternative, less toxic, chemicals. An additional time allowance should be made for the processing of discharge consents for discharges near median lines and at borderlines between MAFF/SERAD and DANI.]
Particular attention is drawn to the prior notification which should be given in all cases of line fill involving radioactive substances, as subsequent discharges may also be subject to the Radioactive Substances Act 1993.
The procedure for obtaining a discharge consent under a PWA is set out below.
Details required:
i. the nature and chemical composition of the substance, including the trade name of the product and the name of the company distributing the product,
ii. the date on which it is proposed to discharge the substance
iii. the quantity, in cubic metres, of the substance it is proposed to discharge,
iv. the maximum rate, in cubic metres per hour, at which it is proposed to discharge the substance
v. the geographic co-ordinates, and height or depth in metres from the lowest astronomical tide (LAT), or the place at which it is proposed to discharge the substance,
vi. the total depth of water, in metres from LAT, at the point of discharge and particulars of the point and manner of discharge,
vii. the respective concentration of each of the chemicals, in parts per million, contained in the substance which it is proposed to discharge,
viii. the toxicity of each such chemical to marine organisms, or the toxicity of the total content of the substance or both,
ix. safety procedures for handling and storage, including line fill and discharge,
x. particulars of any means of dispersal,
xi. and such other information as may be requested.
Proposed concentrations and total diluted quantities in particular should be notified, as they affect the acceptability of the line fill proposals and, in turn, the operational discharge.
Method of discharge
In considering a schedule for discharges, the following points should be noted:
a. near-surface discharges from unmodified outlets at platforms should normally be by cascade over the platform structure to the sea surface;
b. mid -water discharges from platforms are preferable and should normally be made by means of at least two horizontally directed sub-sea nozzles;
c. horizontal discharges from submarine pipelines on the seabed should normally be avoided; pipe ends should be directed upward and have at least two nozzles;
d. if the proposed discharge lies in an environmentally sensitive area, for example, in a fish breeding or nursery area, it may be necessary for MAFF, SERAD or DANI to stipulate either no discharge within certain times of the year, or especially stringent conditions to ensure maximum and effective dilution.
Standard restrictions
The following considerations should be taken into account at all times:
a. Toxicity measurement
When the toxicity is likely to be high or the concentrations of discharged substances above normal, there may be a requirement for samples to be taken and analysed to demonstrate the speed and efficiency of dispersal.b. Fluorescent indicators
Fluorescent indicators should not generally be used in concentrations greater than 15 ppm, or as approved by MAFF, DTI and DANI in specific areas.
Consents for discharges containing fluorescent indicators would normally require that the local MAFF/ SERAD - Marine Laboratory/ or DANI District Inspector be notified immediately before the discharge.c. Manufacture of domestic water from seawater
It is strongly recommended that the operators of all equipment for the manufacture of domestic water from seawater within 1 kilometre of the point of discharge are advised to shut down during a pipeline discharge and for a suitable period thereafter which should not be less than twenty- four hours.
Monitoring
In certain cases, a condition of the consent to discharge may be that samples of seawater are taken at specific locations near the point of discharge. In these cases, operators would be instructed to employ an independent body approved by MAFF/SERAD Marine Laboratory or DANI as appropriate for collection and analysis of the samples and to submit the results to them.
Sample form DisCon 1
[PIPELINE(S) / PROJECT NAME]
Details for Discharge Consent: Form DisCon 1
| Col 1 | Col 2 | Col 3 Col 4 | Col 5 | Col 6 | Col 7 | Col 8 | Col 9 | Col 10 |
| Pipeline Number | Length (m) | Event Anticipated Date of Discharge | Discharge
Location (with Geographic Co-ordinates) |
Discharge Depth (m) | Volume of
Discharge (m3 / hr) |
Discharge Rate (m3 / hr) |
Chemicals to be Discharged | Concentration of Chemicals (ppm) |
Useful addresses
Applications to:
| Department of Trade and
Industry The Secretary of State Department of Trade and Industry Oil & Gas Office 4th Floor, Atholl House 86-88 Guild Street Aberdeen AB11 6AR Marked for the attention of your nominated contact. Telephone: 01224 254055Facsimile: 01224 254019 |
|
| Tel Enquiries Pipeline Policy - Louise Novell Tel: 01224 254052 Fax: 01224 254089 |
|
| Pipeline General Enquiries -
Jacqui Adshead Tel: 01224 254057 Fax: 01224 254089 |
|
| Pipeline Discharge Consents -
Julie Duguid Tel: 01224 254045 Fax: 01224 254019 |
|
| Food Environment Protection Act
(FEPA): General Enquiries - Elaine McLaughlin Tel: 01224 254012 Fax: 01224 254019 |
|
| Pipeline Decommissioning - Ian
Furneaux Tel: 01224 254021 Fax: 01224 254018 |
|
| Enquiries regarding PON XV's to
- Elaine McLaughlin Tel: 01224 254012 Fax: 01224 254019 |
|
| Other government departments: | |
| Health and Safety Executive Chemical & Hazardous Installations Division (Scottish Waters) |
Lord Cullen House Fraser Place Aberdeen AB23 3UB Contact: Tim Ingram |
| Health and Safety Executive Chemical & Hazardous Installations Division (English Waters) |
122A Thorpe Road Norwich Norfolk NR1 1RN Contact: Peter
Runagall |
| Department of Environment, Food and Rural Affairs | Environmental
Protection Division Marine Resources & Licensing Branch Nobel House 17 Smith Square London SW1P 3JR Contact: John Harte |
| Department of Environment, Food and Rural Affairs | Centre for
Environment, Fisheries and Aquaculture Science (CEFAS) Fisheries Laboratory Remembrance Avenue Burnham on Crouch Essex CM0 8HA Contact: Richard
Rycroft |
| Department of Transport, Local Government and the Regions | Ports Division Room 1/27 Great Minster House 76 Marsham Street London SW1P 4DR Contact: Damion
Bagalue |
| Scottish Executive Environment and Rural Affairs Dept. | Marine Environment
Branch Pentland House 47 Robb's Loan Edinburgh EH14 1TY Contact: Lynn Taylor |
| Scottish Executive Environment and Rural Affairs Dept. | Marine Laboratory PO Box 101 Victoria Road Aberdeen AB9 8DB Contact: Derek
Saward |
| Department of Agriculture and Rural Development for Northern Ireland | Fisheries Division Annexe 5 Castle Grounds Stormont Belfast BT4 3PW Contact: Damien
Skillen |
| Department of the Environment for Northern Ireland | Environment and
Heritage Service, Quality Water Unit Calvert House 23 Castle Place Belfast BT1 1FY Tel: 01232 540540 |
| The Welsh Office | New Crown Building Cathay Park Cardiff CF10 3NQ Tel: 029 2082 5111 |
| Ministry of Defence | Mapping and Charting
Officer Office of the Flag Officer Submarines Eastbury Park Northwood Middlesex HA6 3HP Contact: Colin
Bullimore |
| Ministry of Defence (Navy) | Hydrographic Office Nautical Chart Branch 1(c) Taunton Somerset TA1 2DM Contact: Helen
Goodey |
| The Crown Estate (English Waters) |
16 Carlton House
Terrace London SW1Y 5AH Contact: Dr T Murray |
| The Crown Estate (Scottish Waters) |
10 Charlotte Street Edinburgh EH2 4DR Contact: Ian Leaver |
| Maritime and Coastguard Agency | Sunley House 90 High Holborn London WC1V 6LP |
| Maritime and Coastguard Agency | MRCC Aberdeen Search and Rescue Region Aberdeen Blaikies Quay Aberdeen AB1 2PB |
| Maritime and Coastguard Agency | MRCC Yarmouth 4th Floor Havenbridge House Great Yarmouth Norfolk NR30 1HZ |
| Maritime and Coastguard
Agency (Northern Ireland) |
Marine Office The Design Centre 39 Corporation Street Belfast BT1 3BA |
| Non -government organisations | |
| British Telecom | BT Worldwide
Networks Global Networks 18-20 Millbrook Road East Southampton Hampshire SO15 1HY Contact: Stephen
Jackman |
| Joint Nature Conservation Committee | Dunnet House 7 Thistle Place Aberdeen AB10 1UZ Contact: David
Simmons |
| The Isle of Wight County Council | County Hall Newport Isle of Wight PO30 1UD |
| Fishing organisations | |
| National Federation of Fishermen's Organisations | Marsden Road Fish Docks Grimsby South Humberside DN31 3SG Tel: 01472 352141 |
| Scottish Fishermen's Federation | 14 Regent Quay Aberdeen AB11 5AE Contact: Michael
Sutherland |
| Fishermen's Association Limited | c/o Roddy McColl 11 Burns Road Aberdeen AB15 4NT Tel: 01224 313473 |
| Northern Ireland Fish Producers' Organisation Limited | Coastguard Cottages The Harbour Portavogie Co. Down BT22 1EA |
| The Anglo-North Irish Fish Producers' Organisation Limited | The Harbour Kilkeel, Co Down |
Back
| Title
| Table of Contents
Appendix 1 | Appendix 2 | Appendix 3 | Appendix 4 | Appendix
5 | Appendix 6 | Appendix 7 | Appendix 8 | Appendix 9
Appendix 10 | Appendix 11 | Appendix 12 |
Appendix 13 | Appendix 14 | Appendix 15 |
Appendix 16 | Appendix
17
Index Map | Plate 1 |
Plate 2W | Plate 2E | Plate 3W | Plate 3E | Plate
4W | Plate 4E |
Plate 5 | Plate 6
Plate 7 | Plate
8W | Plate 8E | Plate 9W | Plate 9E | Plate 10W | Plate
10E | Plate 11 | Plate 12 | Legend